Congestion management cost around 3.1 billion euros in 2025, and around 35 percent of the curtailed renewable electricity volume was attributable to bottlenecks in the distribution grid. Under the federal government's grid package, grid operators may designate overloaded areas as capacity-limited for up to six years. There, new wind and solar installations forgo part of their compensation, limited to 20 percent of annual generation. The draft provides neither a deadline for grid expansion nor financial consequences for delays.

The Stiftung Klimaneutralität recommends adding the second half to the redispatch reservation: if the grid operator does not eliminate the bottleneck within six years, it bears the compensation costs itself and may no longer pass them on in full to electricity customers via grid charges.

A legal opinion commissioned by the foundation from the law firm w2k considers this allocation of cost responsibility compatible with EU law and constitutional law under certain conditions, and provides the wording for the draft law.

‍